Surajpur Rail Project -0km To 75km
Client: Adani Mining Pvt. Ltd.
Location: Surajpur
Overview
As per directions of Govt. of Chhattisgarh, a SPV, Surajpur Rail Corridor Private Limited (SRCPL) is implementing the railway line for evacuation of coal from various coal blocks in Hasdeo-Arand coalfield.
It is about 75 KM from Sarajpur Road Station the nearest station on Ambikapur-Annupur single line electrified section of Bilaspur Division on South East Central Railway to Parsa East & Kente Basin.
Project Background
Construction of Phase 1, Km 0- 33 started in April’12, commissioned by Jun’15 & train movement started by Oct’14.
Phase 2, Km 33-75 which is split in to 3 sections: Phase-2A (33-54 km)/ Phase-2B (54- 70 km)/ Phase-2C (70-75 km/ Mines Area) out of which 2 sections were commenced Dt: 21.05.2014, Dt: 07.08.2014 & Dt: 07.08.2014 respectively for Phase-2A/2B/2C
Scope of Work
Civil Works
- Formation including Earthworks, Blanketing, Catch water & Side drains and Minor Bridges.
- Structures – RUB’s, ROB’s, Major Bridges, Canal Bridges & Syphons
- Manned level crossings (Non interlocked) with goomties – 6 Nos
- Station Buildings, Staff Quarters, Offices, Stores, Other service buildings, Circulating areas, S&T goomties, SP/SSP rooms, water supply, sanitation and drainage arrangements
- Miscellaneous works like protection works, retaining walls, diversion of roads, platform wall & finishes, cutting of trees, transportation of trees as desired by forest dept., Nulla diversion, etc
Track Works
- Procurement of Ballast
- Procurement of P.Way material, i.e., Rails, PSC Sleepers & Track Fittings etc
- Laying of Track and Points & Crossings
- Welding of Rail Joints
S & T Works
- Multiple Aspect Color Light Signaling (MACLS) system with Electronic Interlocking along with absolute Block working material including – Supply of material including UFSBI, Data logger and execution of same
- Providing communication at stations including landline/ wireless/ control phones on OFC/ 6 Quad cables, walkie talkie sets
- Providing FOIS connectivity through OFC/6 Quad/ BSNL lines/VSAT
Electrical works
- General lighting for proposed crossing stations, yards, offices, staff quarters, water works, level crossings, S&T goomties, SP/SSP platform, street lights
- Power supply works from source to Station Building/Staff quarters
OHE Works
- Due to electrified section at serving station total track are proposed to electrified with 1 X 25 KV OHE – SITC
- (III) FIM – FIM’s like Reinforcement, Rails, Sleeper shall be procured from Railway/RDSO approved vendors