Rail Connectivity to Tiroda Thermal Power Plant

Client: Adani Power Ltd.

Location: Tiroda, Dist-Gondia, Maharashtra

Overview

As a part of this overall scheme, Adani Power Maharashtra Limited (APML) Adani House, Near Mithalakli Circle, Navrangpura, Ahmadabad-380009, a fully owned subsidiary of Adani Power Limited and registered under the Indian Companies Act 1956 proposes to set up a Thermal Power Plant of 1980 MW (3X660 MW) at Tirora village of Gondia district, Maharashtra.

The Proposed Power Plant is located on the south side of Kachewani Railway Station on Gondia –Nagpur Section of South East Central Railway.

Salient Features
Length of siding 26 Kms.
Track Gauge Broad Gauge – 1676mm.
Ruling Gradients 1 in 150 proposed on lead line
Gradients in station Yard and R&D Yard 1 in 1200 or flatter
Rails 52Kg – First Quality
Sleepers PSC Sleepers
Ballast Cushion 250mm
Formation Width cutting 6.83m in embankment & 6.25m
Points & Crossings 1 in 81/2 with Curved Switches and CMS Crossings on PSC Sleepers
Design Speed in Section 50 Kmph (Max.), 30 Kmph (normal)
Curves 30 Nos. with Max Degree is 3
PSC Bridges 24 Nos.
Signalling, Interlocking & Telecomm. Tokenless Block with Multiple Aspect Color Light Signalling (MACLS) with Panel Interlocking
Anticipated Rail Borne Traffic
11.940 MTPA- in 2009-10
13.73 MTPA – in 2010-11
15.79 MTPA -in 2010-11.
(After Doubling the line capacity will increase 48 Rakes on each way theoretically)
Tokenless Block with Multiple Aspect Color Light Signalling (MACLS) with Panel Interlocking
Cargo Handling Movement of Imported Coal, Containers, Liquid cargo etc.
Level Crossings Manned7Nos.Unmanned22 Nos.
Earthwork Filling involved 9,00,000 Cum. (Approx.)
Earthwork in Cutting 3,00,000Cum.(Approx)